SDAC 15-minute Member Test
The SDAC 15 minute Day-ahead Auction will go-live in production on 11 June 2025, for delivery day on 12 June 2025.
Note: The go-live is pending successful testing by all parties and the approval of the Market Coupling Steering Committee (MCSC). Updates on the progress towards go-live will be posted on the Nord Pool website and further project details can be found from from the links here:
In Production, the SDAC Auctions will be run once per day as follows
- Gate closure time (GCT) 12:00 CET/CEST
- Delivery 00:00 - 24:00 the following day
Available Products
The SDAC Auction offers products with resolution of 15, 30 or 60 min Market Time Units (MTU) in all bidding zones.
Market Time Unit (MTU) | Market | Bidding Zone |
15 min 30 min 60 min | Nordic and Baltic | DK1, DK2, FI, SE1, SE2, SE3, SE4, NO1, NO2, NO3, NO4, NO5, EE, LT, LV |
Central Western Europe | AT, BE, FR, NL, AMP, TBW, TTG, 50Hz | |
Poland | PL |
In our SDAC Test Auction we offer curve and block orders submitted directly in our web platform or uploaded via Excel sheets.
- Curve orders are described here. One curve order is permitted in each area per portfolio.
- Block orders are described here. The auction supports normal block orders, profile blocks and linked blocks.
- Exclusive group orders and Flexible Orders are described: Exclusive Groups and Flexible Orders
Note: Always check the Product Specifications on the Nord Pool website under Rules and Regulations for latest information on order types, portfolio restrictions and number of orders supported per Market.
Getting started
To get started, please follow these steps:
- Make sure your user is enabled for the auction (contact [email protected] if you need access)
- Visit the platform following the system links at the bottom of this page
- Insert your username and password to log in (click here help to login)
- Start sending in orders, see User Guide at the bottom of this page
API Access
The Auction API is available for the SDAC auction. For more information, please see our Developers Hub: https://developers.nordpoolgroup.com/
System Links
- System Links available here - Access to the Production and Test URLs
User Guide
Testing in the Nord Pool - Member Test environment (MT)
The table below represents auctions that are available MT and this is the view that will be in place in at SDAC 15-min MTU go-live (and for the start of the Joint Member Test Period). See those cells in the table below highlighted with red borders
Note: Auctions only supporting 60-minute will be discontinued in Production and in MT after SDAC 15-minute go-live. See those cells in the table below with grey shading
Important Notice
Nord Pool is improving the handling of multi-resolution portfolios (15, 30, and 60-minute MTUs).
- Once the Joint Member Test begins on 7 April 2025: All portfolios will automatically support multi-resolution MTUs (15, 30, and 60 minutes). This will also apply in production at the SDAC 15-minute MTU go-live.
- In MT, before the Joint Member Test begins: To test QH auctions with a 15-minute resolution, please contact [email protected] to enable your portfolios. The temporary restriction requiring a fixed MTU per portfolio will be lifted once multi-resolution support is enabled at the start of the Joint Member Test.
Product Name | Product ID | Gate Closure Time (GCT) | MTU | Auction Mode |
Test Nordic Baltic QH Day Ahead | Test_NOR_QH_DA_1 | 14:30 CET/CEST | 15 min 30 min 60 min | Automatically executed (run daily) Test Auctions available every day for multi-resolution testing |
Test CWE QH Day Ahead | Test_CWE_QH_DA_1
| 14:20 CET/CEST | ||
Test PL QH Day Ahead | Test_PL_QH_DA_1 | 14:40 CET/CEST | ||
Nordic Baltic QH Day Ahead |
NOR_QH_DA_1
| 14:00 CET/CEST | 15 min 30 min 60 min | Manually executed during joint Member Tests 07/04/2025 through 15/05/2025 (use these auctions during joint member test period) Product Id matches those in Production after SDAC 15'MTU go-live |
CWE QH Day Ahead | CWE_QH_DA_1 | |||
PL QH Day Ahead | PL_QH_DA_1 | |||
Test NordicBaltic Hour Day Ahead | Test_NOR_H_DA_1 | 14:00 CET/CEST | only | Automatically executed (run daily) Note: These hourly test auctions will be discontinued after SDAC 15min Go-Live |
Test CWE Hour Day Ahead | Test_CWE_H_DA_1
| 14:05 CET/CEST | ||
Test PL Hour Day Ahead | Test_PL_H_DA_1 | 14:15 CET/CEST | ||
Nordic Baltic Hour Day Ahead |
NOR_H_DA_1 | Only run periodically | only | Manually executed Note: These hourly auctions will be discontinued after SDAC 15min Go-Live |
CWE Hour Day Ahead | CWE_H_DA_1 | |||
PL Hour Day Ahead | PL_H_DA_1 |
Test schedule during Joint Member Test period
** See joint member test instructions for more details on the test scenarios – SDAC - Information for Joint Members’ Testing Phase
Day | Date | GCT (CET/CEST) | Member Test Scenario ** |
Mo | 07.04.2025 | 14.00 | Normal Day |
Tu | 08.04.2025 | 14.00 | Full decoupling with shadow auction |
We | 09.04.2025 | 14.00 | Partial decoupling Nordic region (with Nordic regional coupling) |
Th | 10.04.2025 | 14.00 | Second calculation due to bidding error management |
Mo | 14.04.2025 | - | System Updates (manual auction not run) |
Tu | 15.04.2025 | - | System Updates (manual auction not run) |
We | 16.04.2025 | - | System Updates (manual auction not run) |
Th | 17.04.2025 | - | System Updates (manual auction not run) |
Mo | 21.04.2025 | - | Public Holiday (manual auction not run) |
Tu | 22.04.2025 | 14:00 | Daylight Saving Time (Long Clock Change) |
We | 23.04.2025 | 13:30 | Max / min price reached and curtailment |
Th | 24.04.2025 | 13:30 | No liquidity in a given time resolution |
Mo | 28.04.2025 | 14:00 | Normal day |
Tu | 29.04.2025 | 14:00 | Normal day |
We | 30.04.2025 | 14:00 | Normal day |
Th | 01.05.2025 | - | Public Holiday (manual auction not run) |
Mo | 05.05.2025 | 13:30 | High number of blocks |
Tu | 06.05.2025 | 13:30 | Paradoxically Rejected 60’ Curves |
We | 07.05.2025 | 14:00 | Re-execution or Normal day |
Th | 08.05.2025 | - | Public Holiday (manual auction not run) |
Mo | 12.05.2025 | 14:00 | Re-execution or Normal day |
Tu | 13.05.2025 | 14:00 | Re-execution or Normal day |
We | 14.05.2025 | 14:00 | Re-execution or Normal day |
Th | 15.05.2025 | 14:00 | Re-execution or Normal day |
Operational Messages will be published in test environment during exceptional days (when the scenario is deviating from Normal timings